The project’s success underscores Emtel Group’s commitment to pioneering innovative solutions tailored to meet the evolving needs of the telecommunications industry. Through their Solar Hybrid Application, they have demonstrated the potential for renewable energy to drive cost-effective and environmentally friendly operations, setting a precedent for future advancements in off-grid site management.
Description
Site Location
Data
Outdoor
Load
4.5kW
DieselGenerator
30kVA
Mode
Off-grid
DG Run Hours (Daily)
24Hrs
DG running belowi n-efficiency point consumes 1L/kWh (approx.). Therefore, Consumption (L/Month)
3,240L
Diesel Cost/Month(@USD0.56/L)
1,814.40
MaintenanceCost/Month(USD)
245
OPEX/ Month(USD)
2,059.40
OPEX/Year(USD)
24,712.80
Description
Proposed Energy Storage
Data
21.3kWh
SIRIUSModules
3 X 7.1kWh
Module Voltage
48V
Sirius Module Charging Time Capacity
35mins
Actual Charging Time of Sirius per Cycle Based on Available DG Capacity
1.4 hours
Charge Cycles per Day (DG operation)
4
DG Run time per Day (mins)
5.6
Loads operation on SIRIUSESS/Day
18.4Hrs
DieselConsumption @0.27L/kWh(L/Month)
1,193.25
Diesel Cost/Month@USD0.56/L(USD)
668.22
Maintenance Cost/Month–Reduced(USD)
125
OPEX /Month–Reduced (USD)
793.22
OPEX/Year – Reduced (USD)
9,518.64
Downloadable Resources
info@emtel.group
HQ: LIU 1, Office # 14, Dubai Silicon Oasis, Dubai UAE
info@emtel.group
458, Block-B, Canal View Society, Lahore, Pakistan
info@emtel.group
3391 Tolmie Avenue, Richmond, BC V7C 5R1 3567 Bala Drive Mississauga, Ontario L5M 7N2
info@emtel.group
Unit A, Jasmine House, Juniper Dr, London, England SW18 1G
info@emtel.group
5000 Centregreen Way Suite 500 #5168 Cary, NC 27513